fix bad credit florida roofing contractor buy dvd movies online dvds movies online credit report repair fast credit repair bad credit car loans bad credit car loan

Register/Login


Get Updates Via Email






 Subscribe in a reader

Fight AntiSpam

Anti Spam Honeypot

Other Contributors

Srini Uppala
Want to contribute?

Hit Counter



Bookmarks

RSS Feeds


Add to Google
Add to My Yahoo!

- - - - - - - - - - - - - - - - - - - - - - - -
Add to Technorati Favorites
desi Blogs
View Pradeep Sadanapalli's profile on LinkedIn
Who links to me?

Sign My Guestbook

Sign my Guestbook from Bravenet.com 

« Real Estate Destinations 2008 - The show goes on… | Home | Rubber dam across Musi »

ORR connectivity to airport soon

Posted by Srini Uppala | January 3, 2008 | 345 views

1 Star2 Stars3 Stars4 Stars5 Stars (No Ratings Yet)
Loading ... Loading ...

Efforts on to complete work on 4-lane stretch by March-end

HUDA and Outer Ring Road authorities are literally racing against time to provide connectivity to the International Airport at Shamshabad to be inaugurated on March 16.

With Chief Minister Y.S. Rajasekhara Reddy expressing impatience over the delay in ORR phase I work and personally inspecting parts of the stretch on Tuesday, the ORR project officials are working to ensure that basic four-lane connectivity from Gachibowli to Shamshabad is in place by March-end at least, a lag by about two weeks after the airport inauguration. “Though the work is slightly behind the schedule, work cannot be expedited compromising on quality,” officials said.

The 24 km phase I work was entrusted to two international agencies — a Russian firm Transstroy and a Taiwanese firm Continental Engineering Corporation.

Acquisition delays

The project was hit by land acquisition delays with APPA and Forest Department authorities taking their own time to hand over the land.

Besides, rock cutting in the stretch strewn with hillocks proved to be a time consuming affair. Of 55 structures to come up in the stretch, like underpasses, flyovers, bridges, 50 are under various stages of completion. However, seven major structures near APPA, Musi, Shamshabad, Gachibowli would not be ready till June. Yet this would not affect basic connectivity as rams and diversions would be given till these structures are ready, says ORR Project Director Piyush Kumar.

SOURCES:
The Hindu